How long does it take to build a website?
“How long will it take?” — this is usually the second question, right after price. And that’s entirely fair: a site is often needed for something specific — the start of a season, a new service, a trade fair. The honest answer is “it depends on the scope”, but that’s far too little to plan around. So let’s explain what that time is actually made of.
The short answer
A starter site is ready in about two weeks. A business site with several sections, a blog and multiple languages — three to five weeks. An online store — from six weeks, depending on the number of products and on the payment and shipping setup.
For most projects, two to six weeks pass between the first conversation and going live. We fix the deadline in the quote together with the price, so it isn’t “sometime in the autumn”.
What makes the difference between two weeks and six isn’t how beautiful the design is, but the scope: the number of pages, the languages and the integrations. Ten pages instead of five is a few extra days. Three languages instead of one — about a week. A booking system or a connection to your accounting software — more than that, because every step of it has to be tested.
What happens during those weeks
Conversation and quote. We work out who the site is for, what it has to achieve, and what already exists — texts, photos, logo, domain. After that you get a fixed quote with the price, the scope and the deadline. This part usually takes a few days.
Design. We prepare how the site will look — the home page and the main page types. This is the first approval point: until the design is agreed, we don’t move on.
Development. The design becomes a working site: structure, mobile version, speed, forms, SEO essentials. This is the most predictable part — it’s entirely in our hands.
Content. Texts and images go into the site, and we sort out headings, descriptions and the service pages. This stage is often underestimated, even though it’s exactly where it’s decided whether the site will be found in Google later, and whether a visitor understands what you offer in the first few seconds.
Launch and training. Domain, certificate, analytics, checks on phone and desktop. If there’s an existing site, we add redirects so your Google rankings don’t disappear. At the end we show you how to change content yourselves.
What most often stretches the deadline
Content that isn’t ready yet. This is the most common reason a project drags on. That’s exactly why we don’t push the writing onto the client — we talk through what you want to say, and we write it. It’s the same with images: we help choose them and, if needed, propose a solution.
Approvals travelling between several people. If the design has to be agreed with three colleagues who each reply a week later, the calendar stretches all by itself. So we agree at the start on who makes the decision.
Scope that grows along the way. Adding another language or a booking system halfway through is possible, but it’s new work, not a small addition. We always say what it means for the deadline before we start.
Access and technical details. A domain sitting with the previous developer, a forgotten password, hosting nobody can get into any more. We untangle all of that — it’s usually a couple of phone calls, not weeks.
Why we don’t promise “three days”
A site can be put up in a day, if you take a template and drop any text into it. What you get is a page that looks like a thousand others and sells nothing. The time we put into structure, texts and speed is exactly what makes the site work afterwards — show up in Google, load fast, and turn a visitor into a phone call.
When can we start?
If you have a date by which the site has to be online, tell us right away — we can usually plan backwards from it and say whether it’s realistic. For us, website development starts with a conversation, not a form: book a consultation and we’ll talk through your situation, give you an exact deadline and price, and get going.